Final metallurgical test work program for the Fekola Gold Project has been completed as part of the Definitive Feasibility Study (DFS) for the southwestern Mail project, reports Papillon Resources.

The company says that the extensive metallurgical test work program supports the previous decision to implement a conventional primary crush, semi-autogenous grinding and ball mill (SABC) circuit and a gravity concentration and a carbon-in-leach (CIL) on gravity tails processing flowsheet for Fekola.

Project viability

“The recent metallurgical test work results reconfirm the technical viability of the Fekola Project and its simple metallurgical characteristics,” says Papillon’s MD and CEO, Mark Connelly.

Connelly noted that the test work has shown a number of improvements compared with the PFS metallurgical profile. This included small increases in expected recovery, especially at lower head grades, and also significant reductions in cyanide consumption.

“These improvements are expected to be highly beneficial to the project’s economics,” he said.

Key findings

• Direct cyanide gold extraction ranging from 88% to 96%, at a P80 75 μm grind and at various head grades

• Cyanide consumption ranging from 0.24kg per tonne to 0.41kg per tonne of ore, which is significantly less than the average PFS value of 0.72kg per tonne representing an approximate reduction of between 43% and 66% relative to the PFS estimates

• Comminution test work indicates that the ore continues to be classified as hard and moderately abrasive, with minimal variability throughout the ore body.

Comprehensive test

The third metallurgical testing undertaken in July 2013 was the most comprehensive by Papillon.

It was designed to address the final facets of the metallurgical characteristics and performance of the Fekola Project, including variability within the ore body, reagent consumptions and grind size optimisation.

The program was also designed to reconfirm prior test work conducted at Fekola and complement other technical work completed as part of the DFS.

The program, which was conducted by ALS Metallurgy in Perth, Australia comprised eighteen variability composites and a single master composite specifically chosen by Papillon to give representative samples of key sections of the Fekola Deposit.

Sufficient due diligence

Papillon believes that, with this final testing program, the metallurgical analytical work completed to date is sufficient to support the technical due diligence requirements of key financing institutions.

The testing programme also sufficiently supports the company’s internal technical requirements for the development of the outstanding Fekola Project.

Papillon is unlikely to complete any further detailed metallurgical work for the Project, states the company.