Unit 1 of the Kusile power station in the Nkangala District of Mpumalanga is 56% complete, with the overall project 57.9% finished to date, Eskom states in the latest issue of its New Build News.

The first 800MW unit of the 4 800MW power station is expected to be completed in Q4 2015.

Construction highlights

Construction highlights to date include starting the basement excavation in Unit 5’s ACC substation. Construction has also begun on the coal transfer tower.

The boiler on Unit 1 is 46.9% complete and 23.4% complete on Unit 2. Silo construction is 99% complete, while the west chimney is 93.8% complete. The main civil works are 74.7% while Unit 1’s turbine is 69.5% complete.

Kusile will be one of the largest coal-fired power stations in the world once finished, according to Eskom. In a first for South Africa, it will utilise flue gas desulphurisation (FGD) technology.