Main civil and earthworks contractor Grinaker-LTA is proceeding with construction activities on the 68km Majuba rail servitude, according to Eskom in its latest New Build News.
“Structures are progressing well, while the formation on the civil work is improving as well,” reported the utility. The elements to be constructed comprise 96 culverts, nine cattle creeps, 32 agricultural underpasses and overpasses and 18 bridges, one service duct and 40 cattle grids.Incremental launch bridge
Construction of a 300m incremental launch bridge over the Vaal River, the most complex structure in this package, is 30% complete, and is expected to consume 4 100 cubic metres of concrete. The Majuba rail project was initiated after Eskom opted to transport the 32 million tons of coal a year needed for Majuba, Tutuka, Camden, Grootvlei, Kendal and Hendrina via rail as opposed to road.