The box cut for the initial portal to the decline ramps for underground access at the Kamoa copper mine in the Democratic Republic of Congo’s Katanga province has commenced.

Katanga Sprl (MCK)

The contract for the construction of the box cut was awarded to Lubumbashi-based Katanga Sprl (MCK), Ivanhoe Mines reported in a statement.

This contractor has extensive local experience in contract mining and earthworks, and has worked on other significant Katanga copper-mining projects, including Kinsevere, Kipoi and Kolwezi.

Twin declines

Construction of the box cut is expected take about five months, after which development of the first set of twin declines can commence.

The declines have been designed to intersect the high-grade copper mineralisation in the Kansoko Sud area, about 150 m below surface.

Important milestone

“This first development step is an important milestone in Ivanhoe Mines’ schedule to begin realising the tremendous potential of Kamoa’s high-grade resource to deliver meaningful benefits to all of our stakeholders,” said executive chairman Robert Friedland.

“Industry experts recognise that Kamoa is a world-class copper deposit, both in terms of size and grade.” Kamoa is the world’s largest high-grade (>2.5% Cu) copper resource.